Eversheds Sutherland LNG Law Blog
content top

Cameron LNG Requests 15-Month Extension to Complete and Place Terminal Into Service

Cameron LNG has filed a letter with FERC requesting a 15-month extension, to September 19, 2020, to complete and place its liquefaction and LNG export terminal at Hackberry, La., into service. The letter states that Cameron LNG is currently in the final commissioning phase of Train 1 and is completing construction of Trains 2 and 3. On May 20, 2019, FERC authorized Cameron LNG to...

FERC Approves Freeport LNG Train 4 Expansion

FERC has issued an order authorizing construction and operation of liquefaction Train 4 at Freeport LNG’s existing import terminal near the city of Freeport, in Brazoria County, Texas. Train 4 will be able to produce an additional 5.1 million metric tons per annum of LNG (approximately 0.74 Bcf/day) for export. FERC Commissioner Richard Glick issued a dissenting statement criticizing...

Cameron LNG Requests Permission for Commissioning Cargoes

Cameron LNG has filed a letter with FERC requesting authorization for commissioning cargoes of LNG associated with Train 1 LNG production.

Construction at Golden Pass LNG Terminal to Start May 13

Golden Pass Products has filed a letter with FERC stating that construction is expected to begin May 13, 2019 at the proposed Golden Pass LNG export terminal in Jefferson County, Texas.  Qatar Petroleum owns 70 percent of the Golden Pass LNG project and ExxonMobil owns 30 percent....

FERC Authorizes Pre-Filing Review Process for Venture Global Delta LNG

FERC has issued a letter authorizing the pre-filing environmental review process for Venture Global Delta LNG, LLC and Venture Global Delta Express, LLC’s (collectively referred to as Delta LNG). Delta LNG plans to construct a liquefaction facility with a capacity of 20.0 million tons per annum (MTPA) of LNG and a peak capacity of up to 24.0 MTPA and an LNG export terminal facility in...

Final EIS Released for Venture Global Plaquemines LNG Project

FERC has released the final environmental impact statement (EIS) for the Plaquemines LNG export terminal and interconnected Gator Express Pipeline Project, proposed by Venture Global Plaquemines LNG, LLC and Venture Global Gator Express, LLC (together, Venture Global). Venture Global requests authorization to construct and operate a new LNG export terminal along the west bank of the...