FERC Releases Environmental Review Schedule for Commonwealth LNG

FERC has released the schedule for its environmental review of the proposed Commonwealth LNG, LLC liquefaction and LNG export facility and an associated natural gas pipeline in Cameron Parish, La. A draft environmental impact statement (EIS) is expected to be released in May 2020, and a final EIS is scheduled to be released on October 2, 2020. Other federal agencies’ reviews of the project are to be completed by December 31, 2020.

 