Corpus Christi Liquefaction Files Construction Status Report
Corpus Christi Liquefaction has filed a report with FERC covering construction progress at its export terminal at Corpus Christi, Texas, though May 2017. The report states that engineering has progressed to 100.0%, procurement has progressed to 86.9%, and subcontract and direct hire construction work are 34.2% and 37.0% complete, respectively. The total Project has progressed to 65.6% complete against the plan of 65.3%.