Corpus Christi Liquefaction Files Construction Progress Report
Corpus Christi Liquefaction has filed a report with FERC covering construction progress at its LNG export terminal at Corpus Christi, Texas through November 2016. The report states that engineering has progressed to 99.7%; procurement has progressed to 64.1%; Bechtel’s direct hire construction was 18.5%; and the total project has progressed to 47.1% complete.