Sabine Pass Files Construction Status Report
Sabine Pass LNG has filed a report with FERC on the status of construction, through October 2015, at its LNG export terminal in Sabine Pass, La. The report states that Stage 1 (Liquefaction Trains 1 and 2) overall project completion is 96.1% against the scheduled plan of 98.2%. Stage 2 (Liquefaction Trains 3 and 4) engineering is 100% complete, procurement is 99.4% complete, and subcontract and direct hire construction work are 50.4% and 48.5% complete, respectively. Overall project completion for Stage 2 is 76.7% against the plan of 81.8%. The report states that construction progress supports the achievement of substantial completion for Trains 1 and 2 by March 2016 and June 2016, respectively, and for Trains 3 and 4 by April 2017 and August 2017, respectively.