Corpus Christi Liquefaction Files Construction Status Report
Corpus Christi Liquefaction has filed a report with FERC covering construction at its LNG import/export terminal in Corpus Christi, Texas, through October 2015. The report indicates that engineering has progressed to 90.3%, procurement has progressed to 34.6%, and Bechtel’s construction has progressed to 0.8%. The total project has progressed to 25% complete against a planned 19.3%.