Construction Status Report Filed for Corpus Christi LNG Project

Corpus Christi Liquefaction, LLC has filed a report with FERC on the status of construction of its LNG export terminal near Corpus Christi, Texas through July 2015.  The report states that engineering has progressed to 71.9%, procurement has progressed to 25.9%, subcontract and direct hire construction are 0% and 0.1%, respectively, and the total Project has progressed to 18.9% complete against a planned 14.1%.  Construction activities planned for August 2015 are on track.

 