Sabine Pass LNG Files Monthly Construction Status Report

Sabine Pass LNG filed a report with FERC covering construction activities through March 2015 at its LNG export terminal in Cameron Parish, La.  Stage 1 (liquefaction trains 1 and 2) engineering and procurement are 100% complete, and subcontract and direct hire construction work are 65% and 73.4% complete, respectively.  Stage 1 overall project completion is 87.2% against the plan of 87.9%.  Stage 2 (liquefaction trains 3 and 4) engineering is 99.6% complete, procurement is 90.2% complete, and subcontract and direct hire construction work are 38.3% and 23.5% complete, respectively.  Overall project completion for Stage 2 is 62.6% against the plan of 64.4%.

Sabine Pass LNG reports that project progress supports the scheduled substantial completion dates for trains 1 and 2 of February 2016 and June 2016, respectively. The substantial completion dates for trains 3 and 4 are April 2017 and August 2017, respectively. The report can be found here.

 