FERC Releases Environmental Review Schedule for Sabine Pass LNG Stage 3 Expansion
FERC has released the schedule for its environmental review of Sabine Pass LNG’s Stage 3 expansion, consisting of the construction of liquefaction Trains 5 and 6 at its LNG export terminal under construction in Cameron Parish, La., and expansion of interconnected pipeline facilities. FERC plans to issue an Environmental Assessment for the project on August 1, 2014. Other federal agencies having jurisdiction over the project will have until October 30, 2014 to complete their review. FERC’s notice of the schedule can be found here, and the complete docket for the Sabine Pass LNG expansion can be found on eLibrary under Docket No. CP13-552.