Sabine Pass LNG Trains 1 and 2 Over 50% Completed
Sabine Pass LNG filed a report with FERC on construction activities at its LNG export terminal in Cameron Parish, La. The report, covering activities through December 2013, states that Stage 1 (trains 1 and 2) engineering is 90.7% complete, procurement is 82.9%, and subcontract and direct hire construction work are 30.5% and 12.9% complete, respectively. Stage 1 overall project completion is 53.9% against the plan of 56.3%.
For Stage 2 (trains 3 and 4), engineering is now 37.6% complete, procurement is 35.2%, and subcontract and direct hire construction work are 7.8% and 0.0% complete, respectively. Overall project completion for Stage 2 is 20.4% against the plan of 17.4%.
Sabine Pass LNG states that the report supports the achievement of the scheduled substantial completion dates for trains 1 and 2, which remain as February 2016 and June 2016, respectively. Substantial completion dates for trains 3 and 4 are April 2017 and August 2017.
The report can be found here, and the complete docket for the Sabine Pass LNG export terminal can be found on eLibrary by searching Docket No. CP11-72.