Sabine Pass LNG Files Construction Progress Report
Sabine Pass LNG filed its April 2013 report with FERC regarding construction at its LNG export terminal in Cameron Parish, La. The report states that engineering is 55.9% complete, procurement is 48.5% complete, and the overall project is 29.6% complete. The report states that the overall project schedule is progressing ahead of the contractual schedule, with substantial completion dates of February 2016 and June 2016 for Train 1 and Train 2, respectively. Copies of the report can be accessed here, and the complete docket for the Sabine Pass LNG project can be found on eLibrary by searching for Docket No. CP11-72.