Posted on Jun 13, 2019 in
Federal Regulation,
Liquefaction,
LNG Exports |
Comments Off on CCL Requests Extension of Time to Place Train 3, LNG Storage Tank B, and East Jetty in Service
Corpus Christi Liquefaction (CCL) has filed a request with FERC for a two year extension of time, to December 30, 2021, to place liquefaction Train 3, LNG Storage Tank B, and the East Jetty in service. The request states that liquefaction Train 2 is projected to be in service prior to December 30, 2019, five years from the date of FERC’s order authorizing construction and operation of...