Corpus Christi Liquefaction Files Construction Progress Report
Corpus Christi Liquefaction has filed a report with FERC covering construction progress at its liquefaction and LNG export terminal near Corpus Christi, Texas through June 2016. The report states that engineering has progressed to 98.4%, procurement has progressed to 50.6%, Bechtel’s direct hire construction progressed to 8.8%, and the total project has progressed to 36.6% complete.