Corpus Christi Liquefaction Submits Construction Progress Report
Corpus Christi Liquefaction, LLC has filed a report with FERC covering through April 2016 construction progress at its liquefaction and LNG export terminal in Corpus Christi, Texas. The reports states that (i) engineering has progressed to 98.0%, (ii) procurement has progressed to 46.9%, (iii) Bechtel’s direct hire construction through April was 5.7%, and (iv) the total Project has progressed to 33.5% complete.