Corpus Christi Liquefaction Files Construction Progress Report
Corpus Christi Liquefaction has filed a report with FERC covering construction through March 2016 at its liquefaction and LNG export terminal at Corpus Christi, Texas. The report states that engineering has progressed to 97.1%, procurement has progressed to 46.0%, and Bechtel’s direct hire construction has progressed to 4.6%. The total Project has progressed to 32.5% complete.