Dominion Cove Point LNG Files Construction Status Report

Dominion Cove Point LNG has filed its monthly status report with FERC on the progress of construction at its LNG export terminal in Lusby, Md. through reporting period January 2016.  The report states that engineering is 97% complete, procurement is 89% complete, and construction is 24% complete.

 