Cheniere Affiliate to File in March 2016 FERC Application for Corpus Christi Trains 3 and 4

Cheniere Energy affiliate Corpus Christi Liquefaction (CCL) filed a status report with FERC indicating that it plans to file a formal application with FERC in March 2016 for authority to construct its Stage 3 expansion project.  The Stage 3 project facilities, to be constructed at CCL’s LNG export terminal under construction at Corpus Christi, Texas, consist of liquefaction Trains 3 and 4, which together can produce approximately 9 million metric tons/year, an LNG storage tank, and interconnected pipeline facilities.

 

 

 