Sabine Pass LNG Files Monthly Construction Status Report
Sabine Pass LNG filed a report with FERC covering construction activities through September 2014 at its LNG export terminal in Cameron Parish, La. Stage 1 (liquefaction trains 1 and 2) engineering is 99.9% complete, procurement is 99.9% complete, and subcontract and direct hire construction work are 50.9% and 44.5% complete, respectively. Stage 1 overall project completion is 75.6% against the plan of 76.1%. Stage 2 (liquefaction trains 3 and 4) engineering is 88.3% complete, procurement is 63% complete, and subcontract and direct hire construction work are 26.8% and 8.5% complete, respectively. Overall project completion for Stage 2 is 42.8% against the plan of 42.6%. Sabine Pass LNG reports that project progress supports the scheduled substantial completion dates for trains 1 and 2 of February 2016 and June 2016, respectively. The substantial completion dates for trains 3 and 4 are April 2017 and August 2017, respectively. The report can be found here, and the complete docket for the Sabine Pass LNG export terminal can be found on eLibrary by searching Docket No. CP11-72.