Sabine Pass LNG Files Monthly Construction Status Report
Sabine Pass LNG filed a report with FERC covering construction activities through March 2014 at its LNG export terminal in Cameron Parish, La. Stage 1 (liquefaction trains 1 and 2) engineering is 96.0% complete, procurement is 94.6%, and subcontract and direct hire construction work are 37.7% and 21.0% complete, respectively. Stage 1 overall project completion is 63.3% against the plan of 65.1%.
Stage 2 (liquefaction trains 3 and 4) engineering is 55.3% complete, procurement is 44.6%, and subcontract and direct hire construction work are 14.0% and 0.6% complete, respectively. Overall project completion for Stage 2 is 27.1% against the plan of 24.5%.
Completion Dates for trains 1 and 2, remain as February 2016 and June 2016, respectively. Trains 3 and 4 substantial completion dates are April 2017 and August 2017.
The report can be found here, and the complete docket for the Sabine Pass LNG export terminal can be found on eLibrary by searching Docket No. CP11-72.