Posted on Aug 27, 2013 in
Federal Regulation,
LNG Exports |
Comments Off on Sabine Pass LNG Files Monthly Construction Report
Sabine Pass LNG has submitted its monthly construction progress report for July 2013 for its LNG export terminal in Cameron Parish, La., to FERC. The report states that Stage 1 engineering is 72% complete, procurement is 65% complete, and subcontract and direct hire construction work are 25.5% and 3.3% complete, respectively. The overall project completion is 40.2%. The report states...