Posted on May 22, 2013 in
Federal Regulation,
LNG Exports |
Comments Off on Sabine Pass LNG Files Construction Progress Report
Sabine Pass LNG filed its April 2013 report with FERC regarding construction at its LNG export terminal in Cameron Parish, La. The report states that engineering is 55.9% complete, procurement is 48.5% complete, and the overall project is 29.6% complete. The report states that the overall project schedule is progressing ahead of the contractual schedule, with substantial completion...