Sabine Pass LNG Submits Construction Progress Report
Sabine Pass LNG (“Sabine”) has submitted its March 2013 status report to the FERC regarding construction of Sabine’s LNG export terminal in Cameron Parish, La. The report states that engineering on the project is 51.9% complete, procurement is 43.7% complete, and overall project completion stands at 26.4%. On an overall basis, the project schedule is ahead of the contractual schedule, with substantial completion dates of February 2016 and June 2016 for Trains 1 and 2, respectively. The report can be found on eLibrary under Docket No. CP11-72.