Sabine Pass LNG Submits Monthly Construction Progress Report
Sabine Pass LNG, L.P., filed a status report at FERC on the progress of construction of its LNG export terminal in Cameron County, La. The report indicates that engineering was now 39.1% complete; procurement was 30.2% complete; and construction work was 5.0% complete at the end of December. The overall project completion was 18.0% against a target plan of 18.0%. The overall project schedule is progressing ahead of the contractual schedule basis. Early targets for Train 1 substantial completion and Train 2 substantial completion are 43 and 47 months, respectively, against the contractual basis of 49 and 58 months for Train 1 and Train 2. The report is on eLibrary under Docket No. CP11-72.