Sabine Pass LNG filed a status report on construction of its LNG export terminal in Sabine Pass, La., stating that as of the end of September, engineering is 24.2% complete, procurement is 20.6%, and the overall project completion is 11.8%. Sabine Pass states that the overall project schedule is progressing ahead of the contractual schedule basis, with significant acceleration of the...