Southern LNG Requests FERC Vacate Its Authorization for Phase B of Terminal Expansion
Yesterday, Southern LNG requested that FERC vacate its previous authorization for Phase B of the Elba III Terminal Expansion Project at the Elba Island LNG facility. Southern LNG’s filing states that BG LNG, the anticipated subscriber to the regasification and transportation capacity associated with the Phase B expansion, informed Southern LNG that it would no longer need the Phase B capacity, so the expansion would not be necessary. The filing is available in the FERC eLibrary under Docket No. CP06-470.