Details Provided on Scheduled Construction of Neptune LNG Deepwater Port

The Marblehead Reporter offers details regarding the construction of the Neptune LNG deepwater port project, scheduled to commence on July 16. Specifically, the piece notes that construction initially was expected to begin in 2009. However, the timeline was moved up when Suez officials learned that one of the few companies qualified to perform this type of construction has a window of availability this summer, and that another firm has surplus pipe that meets the project’s specifications, precluding the need for Suez to manufacture its own pipe.